[SOLVED] S curve Planned value not egual to project estimates

7 Posts
2 Users
0 Reactions
7,320 Views
(@mcambronvideotron-ca)
Posts: 41
Active Member
Topic starter
 
[#4093]

Hello,
I have a mini project with about 10 task and 207 assigned hours ( seee screen capture) and when i produce the S curve , I see only 29 hours for the coût budgetiser du travail planifié (see s curve figure). Shouldn`t the 207 assigned hours be equal to the planned value ( coût budgetiser du travail planifié)? Am I missing something?
Regards
Thanks


 
Posted : 11 Feb 2017 17H56
(@babynus)
Posts: 14952
Member Admin
 

Mayby a conversion issue.
It seems S-curve is displayed in days but unit displays "h" for hours.
Can you confirm that it is correct if unit is not jours but days ?


 
Posted : 11 Feb 2017 18H39
(@mcambronvideotron-ca)
Posts: 41
Active Member
Topic starter
 

Hello,
It does not seem to be a conversion issue since 207 assigned hours represents 25.8 days of effort ( at 8 hours per day) and the S curve displays 30 hours of planned work.
Would you have any suggestions?
Regrads
Thank for your support


 
Posted : 11 Feb 2017 18H58
(@mcambronvideotron-ca)
Posts: 41
Active Member
Topic starter
 

To complement the issue, the hours on burn down chart seem to be correct.
Regards
Michel


 
Posted : 12 Feb 2017 20H26
(@mcambronvideotron-ca)
Posts: 41
Active Member
Topic starter
 

Hello Babynus,
Have you had the time to investigate the problem? I have added notes to my discussion on the forum and I am not shure you have received them.
Thank you in advance for your support
Regards


 
Posted : 20 Feb 2017 17H39
(@babynus)
Posts: 14952
Member Admin
 

Hi,

Issue is fixed on V6.1.1,
and it is (as I guessed) a conversion issue : days were displayed with unit showing hours


 
Posted : 24 Feb 2017 23H06
(@mcambronvideotron-ca)
Posts: 41
Active Member
Topic starter
 

Merci
Michel


 
Posted : 25 Feb 2017 23H49