Hello,
I have a mini project with about 10 task and 207 assigned hours ( seee screen capture) and when i produce the S curve , I see only 29 hours for the coût budgetiser du travail planifié (see s curve figure). Shouldn`t the 207 assigned hours be equal to the planned value ( coût budgetiser du travail planifié)? Am I missing something?
Regards
Thanks
Mayby a conversion issue.
It seems S-curve is displayed in days but unit displays "h" for hours.
Can you confirm that it is correct if unit is not jours but days ?
Hello,
It does not seem to be a conversion issue since 207 assigned hours represents 25.8 days of effort ( at 8 hours per day) and the S curve displays 30 hours of planned work.
Would you have any suggestions?
Regrads
Thank for your support
To complement the issue, the hours on burn down chart seem to be correct.
Regards
Michel
Hello Babynus,
Have you had the time to investigate the problem? I have added notes to my discussion on the forum and I am not shure you have received them.
Thank you in advance for your support
Regards
Hi,
Issue is fixed on V6.1.1,
and it is (as I guessed) a conversion issue : days were displayed with unit showing hours
Merci
Michel