How do I pause a project that will be inactive for an unknow period of time? I status as On Hold for a project would be nice.
Thanks!
Hello,
currently it is not possible to pause a project .
Just having a status does not release resources for other projects.
What to need to do is create status "Pause", then we have to recalculate the project for in 6 months and finally freeze the planning of the project .
Thanks! That's a good solution but how to freeze the planning?
Hello,
Check the cell " fix planning " on treatment area.
Regards.