Hello,
I'm a new Projeqtor user.
I have a question :
We are several project managers, we'd like each manager can manage his project with all permissions but is only a user on other projects.
Ex :
- manager A have all permissions on project A and is only user who can only modify advancement or is only a redaer on project B
- manager B have all permissions on project B and is only user who can only modify advancement on project A
Is it possible?


 
Posté : 11 Oct PM 18:1010
(@alain-fourastie)
Posts: 366
Membre Moderator
 

HI,
You can create a profil as "GUEST" or " named as you want, with clear right of simple viewing, then to be given to the Manager B allocated on A's project.

Regards


 
Posté : 14 Oct AM 11:1010
(@babynus)
Posts: 14952
Membre Admin
 

Possiblyt it will work with existing "standard" profiles
- Manager A is allocated to Project A as Project Leader and to Project B as Project Member.
- Manager B is allocated to Project B as Project Leader and to Project A as Project Member.


 
Posté : 14 Oct PM 16:1010
(@loline77)
Posts: 6
Active Member
Début du sujet
 

Thanks for your answer.

I have an other question.
I'd like that a project member could change only advancement of this assigned tasks but I do'nt find which specific access I must change.


 
Posté : 24 Oct PM 18:1010
(@babynus)
Posts: 14952
Membre Admin
 

This will be done through the "Timesheet" screen.
User inputs real work, that will automatically calculate progress : progres = (real work) / (ral work + left work)


 
Posté : 24 Oct PM 20:1010
(@loline77)
Posts: 6
Active Member
Début du sujet
 

Thank's.
I found, in french, it's "suivi / imputation". I was looking for "Feuille de temps".


 
Posté : 25 Oct PM 12:1010