V11.1.5 loop when creating milestone type : infinite creation

4 Posts
2 Users
0 Reactions
1,325 Views
jmmbb
(@jmmbb)
Posts: 561
Contributor
Topic starter
 
[#9325]

Hello,

With the new type of expenditure for activities, are these summed up for the related project? for example: does an expenditure of 100 000 € on activity 1 and 50 000 € on activity 2 cause an amount of project expenditure of 150 000 € ?


 
Posted : 17 Feb 2024 14H23
(@marylene)
Posts: 592
Contributor Admin
 

Hello

Yes of course. Everything is always consolidated towards the project.


 
Posted : 19 Feb 2024 15H56
jmmbb
(@jmmbb)
Posts: 561
Contributor
Topic starter
 

This doesn't work for validated cost.

Validated cost for project is always an input, even if some validated cost exist for activities.
Notice it in documentation will be usefull.


 
Posted : 15 Apr 2024 16H15
(@marylene)
Posts: 592
Contributor Admin
 

Hello

Effectively.
We talk about the consolidation of the workload and the costs validated in the manual but it is true that we did not make it two pages...
But we talk about it during our training, so don’t hesitate! 


 
Posted : 15 Apr 2024 16H32