Hello,

With the new type of expenditure for activities, are these summed up for the related project? for example: does an expenditure of 100 000 € on activity 1 and 50 000 € on activity 2 cause an amount of project expenditure of 150 000 € ?


 
Posté : 17 Fév PM 14:022
(@marylene)
Posts: 592
Membre Admin
 

Hello

Yes of course. Everything is always consolidated towards the project.


 
Posté : 19 Fév PM 15:022
jmmbb
(@jmmbb)
Posts: 561
Contributor
Début du sujet
 

This doesn't work for validated cost.

Validated cost for project is always an input, even if some validated cost exist for activities.
Notice it in documentation will be usefull.


 
Posté : 15 Avr PM 16:044
(@marylene)
Posts: 592
Membre Admin
 

Hello

Effectively.
We talk about the consolidation of the workload and the costs validated in the manual but it is true that we did not make it two pages...
But we talk about it during our training, so don’t hesitate! 


 
Posté : 15 Avr PM 16:044