How is possible to change the value of Validated work/ cost ?


 
Posted : 20 Jul 2015 15H32
(@babynus)
Posts: 14952
Member Admin
 

Validated work and cost can be directly entered on activities and project.
The input may be locked depending on consolidation mode choosen on global parameters screen, so that values may only be entered on elementary tasks.


 
Posted : 20 Jul 2015 20H20
(@durou-c)
Posts: 468
Contributor
Topic starter
 

is it possible to unlock validated work and cost after entering a value ?


 
Posted : 21 Jul 2015 9H24
(@babynus)
Posts: 14952
Member Admin
 

On "Parameters" => "Global Parameters", section "Planning", for item "consolidate validated work & cost" select never.
Save.

Then, you'll alway be able to enter validated work and cost, but values will never be consolidated from tasks up to projects.


 
Posted : 21 Jul 2015 18H25
(@durou-c)
Posts: 468
Contributor
Topic starter
 

tks it works


 