[#5842]

Hello,

I have an issue with the WBS order when I am doing automatic import of files. I need to import projects, sub-projects, activities and milestones respectively. I created a batch file to do that . I managed to import them(a timeout had to be put between the activities and the milestones). But every time I do that import, i encounter an issue with the wbs order.

I always have to connect as admin, go to administration and click on "fix issues" several times to fix it. I don't know how to get rid off that issue. I am working with my test instance of Projector. I am scared when people will begin to do imputations.

I thank you in advance for your return.

Best regards


 
Posted : 15 Mar 2019 13H15
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

when I am doing automatic import of files. I need to import projects, sub-projects, activities and milestones respectively. I created a batch file to do that

What exactly did you do ?


 
Posted : 15 Mar 2019 19H34
(@tms)
Posts: 36
Active Member
Topic starter
 

Hello,

I finally fix the issue. It 's working fine.

Best regards


 
Posted : 20 Mar 2019 17H35