Hi,
I can't set an activity to "done". I got the error "the field 'result' is mandatory". Where and when should I fill the result?
Thanks!
Posté : 14/03/2019 6:30 pm
This control is managed through definition of type.
Go to the Activity type, you'll see that there is an option "mandatory result on done status" ...
Posté : 15/03/2019 11:27 am
Début du sujet
Thanks! I must be blind!!! :blink: :S
You guys are awesome!!