Hello,
- PDF export (or print) you can not see the progress bar?
- Is it possible to add a "date startup" allocation of resources. Then use that date in plannifcation? This helps to manage the availability for a startup to another project?
- Manage "list of value" per project? Possible to define the types of activities, milestone documents for each project. Currently it is global.
- Add Opportunity Management. Duplicate risk management or risk having the possibity create a risk or an opportunity?
- Possibility to enter the hours or days in the "imputation" => If it's hours divided by the number of hours per day and stores data in days.
- Possibility to choose which items to display in gantt: Milestone Activity or 2?
- Requirements Management: Linking a requirement has one or more tests, and generate a report "tracability matrix".
- In the menu Finanial Payment, generating an error because it is missing "class Payment"
Thank you
PDF export (or print) you can not see the progress bar?
No, and it's not plan to have one.
Is it possible to add a "date startup" allocation of resources. Then use that date in plannifcation? This helps to manage the availability for a startup to another project?
Already planned as Ticket #40.
Manage "list of value" per project? Possible to define the types of activities, milestone documents for each project. Currently it is global.
Not planned. Would be a major and long re-design of framework, with minor improvement.
Add Opportunity Management. Duplicate risk management or risk having the possibity create a risk or an opportunity?
Could you detail your idea? What do you mean by opportunities in Project Management Context ? What show be followed up and what is the link with risks ?
Possibility to enter the hours or days in the "imputation" => If it's hours divided by the number of hours per day and stores data in days.
It is already possible : see global parameters.
Possibility to choose which items to display in gantt: Milestone Activity or 2?
What is the interest ?
Requirements Management: Linking a requirement has one or more tests, and generate a report "tracability matrix".
It already exists. Look at the reports.
In the menu Finanial Payment, generating an error because it is missing "class Payment"
I don't understand. Is it a bug ? Can you explain ?
PDF export (or print) you can not see the progress bar?
No, and it's not plan to have one.
JCDe=> Shame because without "progress bar" the extract is less useful
Is it possible to add a "date startup" allocation of resources. Then use that date in plannifcation? This helps to manage the availability for a startup to another project?
Already planned as Ticket #40.
JCDe => Ok thanks
Manage "list of value" per project? Possible to define the types of activities, milestone documents for each project. Currently it is global.
Not planned. Would be a major and long re-design of framework, with minor improvement.
JCDe=> Ok I understand
Add Opportunity Management. Duplicate risk management or risk having the possibity create a risk or an opportunity?
Could you detail your idea? What do you mean by opportunities in Project Management Context ? What show be followed up and what is the link with risks ?
JCDe=> Events can have a positive, negative or two at a time. Events having a negative impact represent risks can slow value creation or destruction of the existing value. However, events have a positive impact can remove negative impacts or represent opportunities. By opportunity, is the possibility that an event occurring in, have a positive impact on the realization of objectives and is a leverage factor or support for the creation or preservation of value. Management reinstate the opportunities identified in the context of risk management, strategic thinking and goal setting process.
Sorry for my approximate English if necessary link: http://www.sei.cmu.edu/risk /"> http://www.sei.cmu.edu/risk/
Possibility to enter the hours or days in the "imputation" => If it's hours divided by the number of hours per day and stores data in days.
It is already possible : see global parameters.
JCDe=> I know the general setting, my need is different. I want to follow my project in days (general parameter = day) but allow when entering "real work allocation" to enter hours.
Example: indicates the page "real work allocation" of the week we would like to take hours. The individual time entry and tracking is converted to the BDD hours these days.
This simplifies the input (this is not the resource to do the conversion)
Possibility to choose which items to display in gantt: Milestone Activity or 2?
What is the interest ?
JCDe=> To achieve traceability between WBS and PBS
Requirements Management: Linking a requirement has one or more tests, and generate a report "tracability matrix".
It already exists. Look at the reports.
JCDe=> OK
In the menu Finanial Payment, generating an error because it is missing "class Payment"
I don't understand. Is it a bug ? Can you explain ?
JCDe=> Sorry, this is a bug, when you click on the menu, it appears an error message (missing "class Payment")
Thanks
Opportunity management
request registered as ticket #760
I want to follow my project in days (general parameter = day) but allow when entering "real work allocation" to enter hours.
It is already possible :
unit for real work allocation : = hours
unit for workload : days
Possibility to choose which items to display in gantt: Milestone Activity or 2?
What is the interest ? : To achieve traceability between WBS and PBS
I still don't understand the need, could you explain ?
In the menu Finanial Payment, generating an error because it is missing "class Payment" : when you click on the menu, it appears an error message (missing "class Payment")
I don't know how you got this error as, payment should be disabled (line created on 1.6.0, disable, never activated). Just set the corresponding line in the table "menu" to idle=1 (id=78).
It is already possible :
unit for real work allocation : = hours
unit for workload : days
=> JCDe: Currently, managed by global parameters. My need is different. I need a ressource to enter in hours (if necessary) -> should move combo (for unit workload) parameter general to real work allocation ?
What is the interest ? : To achieve traceability between WBS and PBS
I still don't understand the need, could you explain ?
JCDe: Sorry I begin:
How can we associate a category of product (deliverables) to an activity, and how we can display the list of products (deliverables) to share with the client
My idea:
{TYPE (document type code)} - {PROJ (Project Code)} - {field free} - XXX - {VER}(Version) - {REV} Revision) or XXX is the number managed by the tool according to the project and the document.
Again, thank you for your support :silly: and reactivity 🙂
My need is different. I need a ressource to enter in hours (if necessary) -> should move combo (for unit workload) parameter general to real work allocation ?
I registered the request as ticket #766, but still not sure it is a great idea : having resources input in days and in hours will be a real mess with rounding. Project leader visibility will be a mess and try to imagine resource starting input in hours and finishing in days ...
How can we associate a category of product (deliverables) to an activity, and how we can display the list of products (deliverables) to share with the client
Request registered as ticket #767
I need for documents to have a unique number managed by the tool.
You get something that is quite the same : the document reference. Default format is {PRO}-{TYPE}-Number, but you can change it in global parameters.
IT is not exactely the same, as your request is morez like a version reference, and not document reference. Request registered as ticket #768.
I registered the request as ticket #766, but still not sure it is a great idea : having resources input in days and in hours will be a real mess with rounding. Project leader visibility will be a mess and try to imagine resource starting input in hours and finishing in days ...
JCDe : I agree with you.
I change my requirement: The project manager decides if an activity entered in hours or days. By default it is equal to the value of the parameter generally selected.
You get something that is quite the same : the document reference. Default format is {PRO}-{TYPE}-Number, but you can change it in global parameters.
IT is not exactely the same, as your request is morez like a version reference, and not document reference. Request registered as ticket #768.
JCDe: For me I have a unique document number that is different from managing version / revision