When associating incomming with milestone, planned date for incomming isn't synchronized with milestone planned date.
I think it will be nice to calculate planned date for incomming with associated milestone instead of reporting manually the new planned date (with delay between incomming planned date and milestone planned date like delay between activity and milestone ?).
IT can be done.
Just activate the automation in : Menu Global Parameters, Tab Activity, section Automation, parameter "update incoming from milestone"
😉