Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.
Hi!
First of all congrats to the team behind this web application.
I'm evaluating this application (latest version) and it seems i can not add additional resource assignment to a task.
I can add initial responsible but when i add additional resource to assignment widget. No dropdown list is available to resource field.
I have setup all my list of resources before creating a project / task. could anyone tell me what went wrong?
what needs to be done for the list of resources to be displayed? btw, i have created 31 resources. Thanks!
--Gab
Hi,
Resources must be affected to the project to be able to assign them to activities.
Regards.
Kewl!
Thanks!