Planning xml export...
 
Notifications
Clear all

Planning xml export => tasks transformed to milestones

8 Posts
3 Users
0 Reactions
3,692 Views
(@laurentc)
Posts: 100
Active Member
Topic starter
 
[#7856]

In the planning view exporting to MS project xml does not work properly:
Not fixed planned task with relationships are exported as milestones.
Best regards


 
Posted : 26 Oct 2021 18H44
Gautier
(@gautier)
Posts: 207
Active Member Admin Registered
 

Hello,
Which versions of Projeqtor and MS project do you use?


 
Posted : 27 Oct 2021 11H55
(@laurentc)
Posts: 100
Active Member
Topic starter
 

ProjeQTor 9.3.2 and MS Project 2016.


 
Posted : 27 Oct 2021 11H58
Gautier
(@gautier)
Posts: 207
Active Member Admin Registered
 

Can you give us specific examples of cases, to help correct it. Because we transmit the right information to ms project but the software in certain cases can automatically transform the activity into a milestone if some information is missing in the activity


 
Posted : 27 Oct 2021 12H52
(@laurentc)
Posts: 100
Active Member
Topic starter
 

I propose to send you an anomized SQL export of the database (not before end of this afternoon)?


 
Posted : 27 Oct 2021 13H03
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Hi,

We won't spend time to import / analyse your DB on this free support.
Please provide use case, for instance reproduce on Demo and give us the ids of items (id of exported project)


 
Posted : 27 Oct 2021 13H53
(@laurentc)
Posts: 100
Active Member
Topic starter
 

In your demo database, project PPS01:
Export the planning in MS Project xlm leads to the attached result.
Seems to be a problem with task duration.
The duration exported format is not correct: should be an integer: (see https://docs.NotAllowedScript617ab919e0205microsoft.com/fr-fr/office-project/xml-data-interchange/durationformat-element?view=project-client-2016)

IntegerValue

Exported: PT8H0M0S

Thanks in advance
#L.
 


 
Posted : 27 Oct 2021 18H48
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Hi,

There is no issue with tag : if always contain an integer (7 ou 21)
tag is then not an integer, as it depends on DurationFormat

What is strange is that when I open the xml with MS-Project 2019, all is fine, I mean I get same planning as on projeqtor.
 

So is it difficult to tell if it is a projeqtor issue or an MS-Project issue ?

 


 
Posted : 29 Oct 2021 13H16