In the planning view exporting to MS project xml does not work properly:
Not fixed planned task with relationships are exported as milestones.
Best regards
Hello,
Which versions of Projeqtor and MS project do you use?
ProjeQTor 9.3.2 and MS Project 2016.
Can you give us specific examples of cases, to help correct it. Because we transmit the right information to ms project but the software in certain cases can automatically transform the activity into a milestone if some information is missing in the activity
I propose to send you an anomized SQL export of the database (not before end of this afternoon)?
Hi,
We won't spend time to import / analyse your DB on this free support.
Please provide use case, for instance reproduce on Demo and give us the ids of items (id of exported project)
In your demo database, project PPS01:
Export the planning in MS Project xlm leads to the attached result.
Seems to be a problem with task duration.
The duration exported format is not correct: should be an integer: (see https://docs.NotAllowedScript617ab919e0205microsoft.com/fr-fr/office-project/xml-data-interchange/durationformat-element?view=project-client-2016)
IntegerValue
Exported: PT8H0M0S
Thanks in advance
#L.
Hi,
There is no issue with tag : if always contain an integer (7 ou 21)
tag is then not an integer, as it depends on DurationFormat
What is strange is that when I open the xml with MS-Project 2019, all is fine, I mean I get same planning as on projeqtor.
So is it difficult to tell if it is a projeqtor issue or an MS-Project issue ?