The black line of project in planning start after the first activity and stop before the last activity. I think black line depend on date in project and not the first activity, so when i reduce planning black line give wrong planning.
In picture you can see a project with 3 activity.
Best regard's
P.S. : i'm newbie in ProjectOr Ria, i think it's a good tool.
The "black" line is the parent item.
This line is not dynamically updated. It is calculated through planning calculation.
Run planning calculation to fix this.
OK, sorry.
In fact i think that yesterday when run calculate planning, the project list is empty. Today i see all project in the list. Calculate is OK.