[SOLVED] Cost and Works left work error

3 Posts
2 Users
0 Reactions
1,828 Views
(@karl-binet)
Posts: 128
Active Member
Topic starter
 
[#7521]

Hi,

V9.1.3

In a activity I have incorrect value in Cost and Work Assigned Work 137h - Real 41.25 total 95.75h but left works shows 115H

I'm having this issue in other project/activities.

I did he Fix Issues in consistency checks, did not change anythings

Any hint on how to solved this issue 

Regards


 
Posted : 03 May 2021 17H10
babynus
(@babynus)
Posts: 14957
Main Contributor Admin
 

IT is not an error.
It is just that resource changed Left work to point out he will not finish on time.
Left is not always Assigned - Real (otherwise we yould not need reassessed)


 
Posted : 04 May 2021 20H27
(@karl-binet)
Posts: 128
Active Member
Topic starter
 

Great, i understand, i looked at all the activities attach to this one and i found an activity that hours were manually added.

Thanks


 
Posted : 05 May 2021 21H30