[v6.0.1 acceptance review] - milestone fix

3 Posts
2 Users
0 Reactions
2,366 Views
(@verges)
Posts: 85
Active Member
Topic starter
 
[#3885]

in the real project life , projects begin whereas we are in advance phase.

we don't have the possibility in this version to fix a "reference planning" before the "today date"...

is it possible to choose a date of the refernce planning in order, for example" to fix a reference planning for the T0 of the project...

This action permits to fix the fist miletone date at T0 of the project even if we have already begined the project


 
Posted : 30 Nov 2016 21H04
(@babynus)
Posts: 14952
Member Admin
 

Hi,

This is a very specific use case.
To take this into account we propose to be able to enter baseline date as long as no baseline already exist for the project.
Hope this fits the need.

Request is Ticket #2405


 
Posted : 01 Dec 2016 14H06
(@verges)
Posts: 85
Active Member
Topic starter
 

[v6.0.3 acceptance review] - OK, thanks you. Now is possible to tag a past baseline.


 
Posted : 08 Dec 2016 18H24