In same way of 45° curve , it would be possible to fix the reference planning at T0 of the projet before "today date".
Validated workload shall be fix in the past ...
Posté : 30 Nov PM 21:1111
This is not an issue with 45° grash but with baseline.
Already recorded as Ticket #2405
Posté : 1 Déc PM 14:1212
Début du sujet
[Acceptance review 6.0.3] : Ok . Now is possible to fix a planning in the past. You're right, is not a 45°curve issue but a baseline configuration issue. To fix a planning in the past is possible only if there are not baseline already fix.