As the screenshot shows, if there is no work in the week, the summary line is shown with green background.
Visually, Green highlight is associated with 100% FTE work done.
That's not the same as there is no work assigned or done,
Therefore, cells with zero work should be shown with darker gray color (just like a holiday column).
It is just because no resource is selected (maybe connected user is not a resource)
So his capacity is zero ! And sum is equal to capacity 😉 so sum is green
Yes, of course I had guessed that already, but that's not a good logic, because green is NOT used to denote OK condition in ProjeQtor: It is specifically used to denote 100% FTE used condition. And the 0/0 condition is not the same as that!
Possibly...
But what is sure is that resource with capacity to 0 is not real use case.