1) a budget must be approved ot be used 2) A budget item can be used by any project, there is no restriction
We do not provide free support on this forum for old version. We only support latest stable (current is V12.2.3) Only way to get some support on old...
You have the answer Extension missing: openssl. You need to install this extension to use SSL encryption
Ticket #10567 is fixed. Fix is available through subscription.
Hi, The "long" part is not the save, it is the replan of the project planning. You can try and disable automatic planning, then manually execute pla...
Hi, Network tab does not tell anything. Please search console for errors, and also serach for errors in log files (projeqtor, apache, ...)
Just select the "Budget item" is the Project Expense field.
Ticket #10585 recorded
reorder the components in alphabetical order Where ?
And what version are you using ? I see empty csrfToken at end of URL. This cannot be the case on latest stable release V12.2.3. We bring some free ...
Are you sure the issue occurs when saving Ticket ? Log says "id '.' is not numeric for class DocumentVersion"
You should find the reason written in the log file. Please post it here so we can help. But I guess it is issue with write rights on projeqtor fil...
OK, Notification on Activity-Progress has some issues. Ticket #10550 recorded
Hi, Notifications are triggered on Date So in your case, when "Dade de début demandée" is passed. This date is rarely defined. So you show try a...
Thanks for additional info. I added ticket for further analysis as I cannot reproduce such behavior on default config.
I'm adfraid, no, that's no very clear. Could you please add screenshots ?
Can you please check that the admin user (id #1) has access to menu "Administration" ?
The log out of first user is probably due to Cron restart that fails. The cron is designed to restart automatically if it is stopped unexpectedly.
Hi, not in the Activity Feed, that is dedicated to major updates (notes add, status change, mail sent) but you can find the information of which fie...
To install a plugin, just go to the plugin management page. There, you'll be able to upload and install the plugin.
Hi, All seems correct. Difficult to find source of issue. (i contacted you through email)
What is the default profile of user copying the template, the value on Resource or User screen ? Can you please show screenshot of this resource and ...
Hi, I tested with standard configuration, there is no issue for project managers to copy template project. I also tested use case on Demo : all work...