Hi, i found the problem why the planned work wasn't displayed. The ressource was booked with too many activities at a rate of 100% so it wasn't po...
Thanks for your answer. I had calculated the planning but as soon there si some work assigned (in my case two days) the planned dates are not filled. ...
Hello, Too many tests doesn't help to focus. You were right, i mismanaged the way i was using the functionnality before encountering this "problem...
Great, thank you. Unfortunately my company won't allow me to start a sponsorship for this evolution..
Thanks for your answer. do you think it could be interisting of posting my question on the "propose evolution" category ?
Great, i didn't think to check that screen. Quality process is important but as soon as it's not a common pratice and / or a priority in a company,...
Thanks for your quick answer, we will manage with this beaviour !
Hi, thanks for your answer.
Hello, thanks ! Ok i understand. The columns you choose on the standard Gantt chart has an impact on the content of the report... i wasn't aware of...
Ok but in the pictures there is a difference of vision : The admin see a tab plus the planning with colors and "boxes" whereas the user see just a tab...