Hello,

i have a problem with the planifications. I should have modify something because it was working perfectly before.

I have an activity planned with "as soon as possible" :

When i'm generating a planning with the date 08/08/2020 :

nothing happened for the planned date of the activity, it's still 02/10/2020.

Before it was working fine, the date was changed for 08/08/2020 but now it's working like if i've planned the activity "don't begin before the validating date", whereas it is "as soon as possible".. If i'm generating a planning with, for example, the 25/10/2020, it's ok the planned date is modified..

Thanks a lot !


 
Posté : 24 Août PM 13:088
(@alain-fourastie)
Posts: 366
Membre Moderator
 

Hello,

I suggest to you to read the friendly manual.
In your first case, planification was able to be hopefully as validated
Bur unfortunatly, constraints come along ( like disponibilty of resources and so on) so planified dates could not be anymore as valided ( whished)
Projeqtor is a dynamic tool confronting what you expect and what you can REALLY DO.

Pleasure.


 
Posté : 24 Août PM 16:088
(@brunof782)
Posts: 45
Active Member
Début du sujet
 

Hello,

Too many tests doesn't help to focus. You were right, i mismanaged the way i was using the functionnality before encountering this "problem" that wasn't one.

thanks for your answer anyway.


 