Plan to a specific date

Thanks for your quick answer. In my case, I have two projects with planning mode "regular between two dates", and in this case, just the last solution...

11 years ago
Topic
Replies: 14
Views: 11563
Reply
[SOLVED] Milestone

You are right, thanks babynus.

11 years ago
Topic
Replies: 2
Views: 2656
Reply
Problem on meeting planning

I checked it and no "fixed planning" is enabled. It is a strange behavior. 👿 So for me, any meeting should be planned...as a meeting. My wor...

11 years ago
Reply
11 years ago
Reply
Update plan after finish a task before planified date

Is it possible to include this management act as an automatic task on the road map? B)

11 years ago
Reply
Report

In my opinion, the need is show all projects which were bad plan at work estimation level. I think some PM need to have this information. But no pr...

11 years ago
Reply
Recalculation Auto

So, I cannot refresh automatically all plannings. 👿 Could you consider this idea as an possible evolution?

11 years ago
Reply
11 years ago
Reply
Report

Have you plan this evolution on your road map or it is not necesary in your opinion?

11 years ago
Reply
Problem on meeting planning

If I recalculate all projects involved on this disponibility problem, why the problem is not solved ? because if my understanding is right, all meetin...

11 years ago
Reply
Do an action for a special status/event

Yes, but my topic is a propose evolution, it was just an idea. :blink:

11 years ago
Reply
Recalculation Auto

But the user is not a parameter of this function, how can I use the function PlannedWork->plan() into a shell script?

11 years ago
Reply
Half Day Off

This solution is running without problem except if I enter real work in the future, the planning was not recalculate automatically. I need to refresh ...

11 years ago
Topic
Replies: 1
Views: 2324
Topic
11 years ago
Replies: 4
Views: 2638
Topic
Reply
Problem on meeting planning

Ok that's right, PM_MLT is already busy so how can I plan a meeting? Is it not possible during implementation process? altough meeting has a priority ...

11 years ago
Reply
Do an action for a special status/event

For me an action is something to do, no an action as ProjeQtOr used it. In French just to clarified. :blush: Par exemple, je voudrais programm...

11 years ago
Reply
Planning Problem

Thanks for the clarification. If I define a starting date with ASAP planification mode, the starting date is just an indication to plan (ie at leas...

11 years ago
Topic
Replies: 10
Views: 7425
Reply
Do an action for a special status/event

Hi Babynus, Sorry for my english, I try again. :blush: I would like do an action following the outcome of an event. For example, if my task...

11 years ago
Reply
Planning Problem

There in no impossibility to plan a task before current day. But if I'm creating the task today, I didn't work on this task last friday so the ta...

11 years ago