Plan to a specific ...
 
Notifications
Clear all

Plan to a specific date

15 Posts
3 Users
0 Reactions
11.6 K Views
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 
[#2851]

Hi

I plan project for IT System, and sometimes, we need a specific date for some tasks (i.e., a window maintenance...) but I didn't simulate it on ProjeQtOr, is it possible to force a task to a specific date?

Thanks


 
Posted : 05 Jan 2016 19H17
(@babynus)
Posts: 14952
Member Admin
 

You have several ways :
- planning mode = not start before, and hight priority (1)
- planning mode = regular between dates (will have highest priority) => my advise
- set a fixed milestone and add task with only milestone as predecessor, with plannong mode = fixed duration
- define task as a Meeting => also a very good alternative


 
Posted : 05 Jan 2016 19H22
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

Thanks for your quick answer. In my case, I have two projects with planning mode "regular between two dates", and in this case, just the last solution worked for me.

As a suggestion, I think a new planification mode could be create to avoid to change the priority and/or the planification mode to force a date to a task, are you plan this on your road map?

Thanks again.


 
Posted : 06 Jan 2016 12H01
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

Hi Babynus, do you think it is a possible evolution?


 
Posted : 11 Jan 2016 16H12
(@babynus)
Posts: 14952
Member Admin
 

I'm afraid this planning mode will not be possible.
Imagine you define a "fixed" tasks on 1 day with 2 work days ...
Or you fix the task, and assign it to a resource who is out this day ?


 
Posted : 11 Jan 2016 17H08
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

You are right but in the real world, sometimes we need plan to a specific date that's why in ProjeQtOr, some plannings cannot reproduce the reality. Nothing can be done now.


 
Posted : 12 Jan 2016 14H46
(@babynus)
Posts: 14952
Member Admin
 

One possibility : if you're sure the work has to be done on that date and will be done on that date : directly enter real work !


 
Posted : 12 Jan 2016 14H58
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

Yes but it is not displayed on the Planning, we can enter a real work but the planning is wrong.


 
Posted : 12 Jan 2016 18H27
(@babynus)
Posts: 14952
Member Admin
 

No, replan and you'll see : planning is good.


 
Posted : 12 Jan 2016 19H13
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

How the planning could be right if you have no validated/assigned work for the ressource (i.e.because you just enter a real work allocation)?

In my understanding, the planning is created when you have a validated work which is assigned to a ressource and after check the disponibility of this ressource, am I wrong? Without an assigned work, no planning is generated.


 
Posted : 12 Jan 2016 19H33
(@babynus)
Posts: 14952
Member Admin
 

How the planning could be right if you have no validated/assigned work for the ressource (i.e.because you just enter a real work allocation)?

Enter real work does not forbit to define validated work and requires to define an assignment 😉

In my understanding, the planning is created when you have a validated work which is assigned to a ressource and after check the disponibility of this ressource, am I wrong? Without an assigned work, no planning is generated.

No, planning is defined form Left wor, an integrates real work also.

Just have a try, you'll see.


 
Posted : 12 Jan 2016 20H56
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

No, planning is defined form Left wor, an integrates real work also..

Yes, you are right, (I use it to manage the indisponibility as half day, holidays...etc) but every solution has a disadvantage, and for your solution, I think it is not clear, because you will have some tasks planned with the "traditional" way (task ---> assign ---> work ...etc) and others with the real work allocation, so I think it is more complicated to understand the planning.

Thanks for share your tips.


 
Posted : 13 Jan 2016 15H16
(@noisette)
Posts: 24
Active Member
 

I read this topic with interest. I have a quite similar question. I have an activity which is annual task. I want to assign 3 hours to Charlotte (a resource) each monday morning.
How could I plan it?
I would prefer not to use "real work affectation" because as El Wallos said : "

For your solution, I think it is not clear, because you will have some tasks planned with the "traditional" way (task ---> assign ---> work ...etc) and others with the real work allocation, so I think it is more complicated to understand the planning.

Thanks
All the best
Christophe


 
Posted : 30 Dec 2016 13H21
(@babynus)
Posts: 14952
Member Admin
 

I want to assign 3 hours to Charlotte (a resource) each monday morning.
How could I plan it?

You cannot with an activity.
Recuring activities are not integrated yet.
It is subject of ticket #1053.

Possibly you can use reccurring meeting, but it's not excactly like planning an activity.


 
Posted : 30 Dec 2016 15H32
(@noisette)
Posts: 24
Active Member
 

This recurrent activity will be VERY useful.
Thanks.
Christophe


 
Posted : 30 Dec 2016 16H32