Sorry : in fact you must assign those 31 days to your developer :
You must set the project workload in field "work" instead of field "duration".
I guess it is ticket #1815 : Will be definitively interesting, and potentially would solve our issue It is targetted for 5.4.0, can't wait for thi...
Sorry I should have searched first First ticket targeted for V5.4.0, great ! Thanks
Thanks Since we do this kind of operation very often, it will be a lot of confusing manual operations (and my colleagues will hate me for that 🙁 ...
In "planning" view, click on calculate button Check manual :
I want to ask about planned ?. How to display the date in the plan. According to the document, it is automatically added. But I entered full, start da...
Not the first 3 ideas, apparently It is more like 2 days have been removed from "real work" but not taken into account for some reason Maybe a bug...
What you propose will not work. It will if you enter days correclty day by day and never enter work backward. OK that's true :-/ But instead of t...
Would it be easier to have 1 field in work and plannedwork table that would indicate the progress in the activity ? (so for Activities only) Progress...
Why have it on planning element as you have it on Activity ? (this is a 1on1 link between both) Sorry, rather in in PlannedWork or in Work table, so...
I want to distinguish the planned days in normal validated days from the planned days that are overspentYou cannot. Only margin will give you the info...
Hello If I understand your explanation : - I define an indicator on activity ("reassessed work compared to validated work"), with the threshold of 1...
I tested 5.2.3 this morning. The issue is fixed, it works great, thanks 🙂
Great 🙂 Thanks
Reproduced on demo : Project : RegularFullDays Resource : albert Assigned 3 days "regular in full days" in february 2016 -> The issu...
Yes I have recalculated the planning. Seems weird to me, if I do a test on a newly created activity, it works well. But the issue appears on some p...
Yes, but even with "regular in full days", 0.1 days are planned : Is there any reason why the planning calculation would to that ?
That is exactly what I did :
Thanks for this helpful doc That is what I understood, I should have : But instead the last day is splitted in 0.1 or 0.2 workloads like ...