[SOLVED] Duration in planning mode

Sorry : in fact you must assign those 31 days to your developer :

10 years ago
Reply
[SOLVED] Duration in planning mode

You must set the project workload in field "work" instead of field "duration".

10 years ago
Reply
Sharing resources between business units

I guess it is ticket #1815 : Will be definitively interesting, and potentially would solve our issue It is targetted for 5.4.0, can't wait for thi...

10 years ago
Reply
Searching projects in selector

Sorry I should have searched first First ticket targeted for V5.4.0, great ! Thanks

10 years ago
Topic
Replies: 2
Views: 4027
Reply
Sharing resources between business units

Thanks Since we do this kind of operation very often, it will be a lot of confusing manual operations (and my colleagues will hate me for that 🙁 ...

10 years ago
Reply
[SOLVED] How the planned dates?

In "planning" view, click on calculate button Check manual :

10 years ago
Reply
[SOLVED] How the planned dates?

I want to ask about planned ?. How to display the date in the plan. According to the document, it is automatically added. But I entered full, start da...

10 years ago
Topic
Replies: 4
Views: 4417
Reply
Real in progress vs real in assignment

Not the first 3 ideas, apparently It is more like 2 days have been removed from "real work" but not taken into account for some reason Maybe a bug...

10 years ago
Topic
Replies: 3
Views: 3825
Reply
Overspent days in planned days

What you propose will not work. It will if you enter days correclty day by day and never enter work backward. OK that's true :-/ But instead of t...

10 years ago
Reply
Overspent days in planned days

Would it be easier to have 1 field in work and plannedwork table that would indicate the progress in the activity ? (so for Activities only) Progress...

10 years ago
Reply
Overspent days in planned days

Why have it on planning element as you have it on Activity ? (this is a 1on1 link between both) Sorry, rather in in PlannedWork or in Work table, so...

10 years ago
Reply
Overspent days in planned days

I want to distinguish the planned days in normal validated days from the planned days that are overspentYou cannot. Only margin will give you the info...

10 years ago
Reply
Overspent days in planned days

Hello If I understand your explanation : - I define an indicator on activity ("reassessed work compared to validated work"), with the threshold of 1...

10 years ago
Reply
Regular in full days plans partial days

I tested 5.2.3 this morning. The issue is fixed, it works great, thanks 🙂

10 years ago
Reply
10 years ago
Reply
Regular in full days plans partial days

Reproduced on demo : Project : RegularFullDays Resource : albert Assigned 3 days "regular in full days" in february 2016 -> The issu...

10 years ago
Reply
Regular in full days plans partial days

Yes I have recalculated the planning. Seems weird to me, if I do a test on a newly created activity, it works well. But the issue appears on some p...

10 years ago
Reply
Regular in full days plans partial days

Yes, but even with "regular in full days", 0.1 days are planned : Is there any reason why the planning calculation would to that ?

10 years ago
Reply
Regular in full days plans partial days

That is exactly what I did :

10 years ago
Reply
Regular in full days plans partial days

Thanks for this helpful doc That is what I understood, I should have : But instead the last day is splitted in 0.1 or 0.2 workloads like ...

10 years ago
Topic
Replies: 14
Views: 8634
Topic
Replies: 12
Views: 8641