Solve using Planning Calculation. Sorry for my confusion.
How can I change Date Planned? I cannot do it. I have not milestone. I have each activities related to the next. I must set validated date?
See attachments for green bar of Planning. Resource in attachment file has not committed on 13 and 15 April (sickness) but Planning shows a filled gr...
Ok, but in my Planning I see Real work committed also for sickness days. I believe that green bar was filled only for committed days. Thanks.
Thanks, so "Monthly planning resource/project" is ok but I must set for each activity an Assignment resource with a number of day assigned otherwise I...
Is not possible?
Found solution. I must manage correctly left work.
Solved, I must logout and login to view updated functions.
I use 5.1.5 version
How can I edit planned in my activity? It's disable for editing.
No, I meant to configure email send differently among project. For example, if I create an Activity for Project "X", I would send email to Project Le...
I understand. So, if I am administrator as profile, I can't have Project Leader profile on a specific project, right? Only solution is to add me in a...