[SOLVED] Unable to create new project, activity, milestone

Exact. Just change the view and return on planning view activate the new item button. Many thanks.

6 years ago
Reply
[SOLVED] Unable to create new project, activity, milestone

I've clear the browser cache. Same problem. Find in attached file the browser console error message.

6 years ago
Reply
[SOLVED] Unable to create new project, activity, milestone

I've an administrator profile. No issue in the log file, just the connection trace. No actin when I click on the button (no menu like "create new pr...

6 years ago
Topic
Replies: 1
Views: 1967
Reply
Resource end of contract

So can you confirm availibilty report doesn't reflect the truth ? Is it possible to have a new evolution request : had a field to insert the departure...

7 years ago
Topic
Replies: 3
Views: 2198
Reply
Load of a resource is not counted in the calculation

Many thanks babynus. Everything works perfectly ! Evolution : is it possible to have a message when task can't be planned (with explanation) ?

7 years ago
Reply
Load of a resource is not counted in the calculation

Yes it's a resource view. Some of resources are affected on some tasks. Screenshot in attached file. Upgrade to v7.3.4 version --> no more b...

7 years ago
Reply
Load of a resource is not counted in the calculation

I'm administrator and the specific ressource is "Team member" Log file in attached file

7 years ago
Reply
Load of a resource is not counted in the calculation

Capacity of the ressource : 1 ETP Project assignment : 100% Task assignment : 1 day As you can see on the picture attached, some tasks don't have...

7 years ago
Reply
Load of a resource is not counted in the calculation

1) Fix planning isn't checked on project (and on project on superior level). 2) WBS structure seems correct. But Consistency Check report oan error a...

7 years ago
Reply
Load of a resource is not counted in the calculation

Hi, Yes I did. I run it today but still same problem. I've the same problem on differents projects. Same process to create project and task but on so...

8 years ago
Reply
Load of a resource is not counted in the calculation

New try today on another project. Creating a new task then assigning a ressource (and charge) to this task. Re calculate the project. Still no sche...

8 years ago
Reply
Load of a resource is not counted in the calculation

I've change left work --> still have the project icon center white. (not orange) Then i (re)calculate the planning --> still have the project i...

8 years ago
Reply
Load of a resource is not counted in the calculation

This is not an administrative project but an internal project.

8 years ago
Reply
Load of a resource is not counted in the calculation

It's exactly what I did but same problem. I also validate the planning. I haven't got any scheduled date in the task. Validate date (start and end) ...

8 years ago