a substantive activ...
 
Notifications
Clear all

a substantive activity Even though I read the manual, I don't really know how t

7 Posts
5 Users
0 Reactions
3,575 Views
(@chaours)
Posts: 45
Active Member
Topic starter
 
[#7675]

a substantive activity Even though I read the manual, I don't really know how to enter this kind of activity. For example an activity of management of mails (apart from particular projects let's say that the management of mails is any project combined) I tell myself that management with the "recurring" schedule is good for doing that can you direct me please thank you

***
une activité de fond 

j'ai beau lire le manuel je ne sais pas trop comment rentrer ce genre d'activité. 
Par exemple une activité de gestion de mails (en dehors de projet particuliers disons que la gestion de mails est tout projet confondus)

je me dis que la gestion avec le planning "récurrent" est bien pour faire ça

pouvez vous m'aiguiller svp merci 


 
Posted : 06 Aug 2021 19H17
(@chaours)
Posts: 45
Active Member
Topic starter
 

I think I have found to manage my fund tasks I created a large global project in which I put all my other projects in sub-project and including a recurring task for the background task

it has to work well! 🙂
phew ...!

***
je pense avoir trouvé pour gérer mes taches de fonds j'ai créé un grand projet global dans lequel j'ai mis en sous projet tous mes autres projets et dont une tache récurrente pour la tache de fond

ça à l'air de bien marcher ! 🙂
ouf...!


 
Posted : 06 Aug 2021 21H09
(@alain-fourastie)
Posts: 366
Member Moderator
 

HI,

Yes it is a good solution among all solutions


 
Posted : 09 Aug 2021 11H16
(@emgenet)
Posts: 2
New Member
 

Hello,
I may be silly, but how do you create a recurring task, as a recurring item, I only see meetings?
Thanks in advance.

Bonjour,
Je suis peut-être idiot, mais comment daites-vous pour créer une tâche récurente, en item périodique, je ne vois que les réunions ?
Merci d'avance.


 
Posted : 28 Apr 2022 12H14
(@emgenet)
Posts: 2
New Member
 

Hello,How to assign recurring charges? It appears well in the detail of the assignment, but not in the global nor in the schedules.

Thanks.


 
Posted : 28 Apr 2022 12H44
(@babynus)
Posts: 14952
Member Admin
 

Hi,

ProjeQtor does not manage recurring tasks, but can manage single tasks with recurring planning.
With planning mode "Recurring" you can define planned work on a weekly basis (0,5 day every wednesday and every friday for instance)


 
Posted : 28 Apr 2022 16H21
(@marylene)
Posts: 592
Member Admin
 

To create your recurring task, select the "recurring" planning mode on your activity in the progress > management section
Then fill in the daily workload over a working week which will automatically apply to the total duration of the project on which it depends.

you find this information in our online manual or by pressing the F1 key directly from your ProjeQtOr session
Planning mode​​​​​​​
Recurrent assignment


 
Posted : 28 Apr 2022 16H30
Share:

Scroll to Top