Forum

Action Managment - ...
 
Notifications
Retirer tout

Action Managment - copy of linked elements

8 Posts
3 Utilisateurs
0 Reactions
8,864 Vu
(@psc)
Posts: 14
Active Member
Début du sujet
 
[#3085]

Hello,
in project management it is possible to copy the structure of a project, meaning to duplicate linked activities.
Is it possible to have this option also for action management? I would like to have linked activities duplicated (for working with action templates).
Thanks a lot!


 
Posté : 22 Fév PM 21:022
(@babynus)
Posts: 14952
Membre Admin
 

It is already possible


 
Posté : 24 Fév PM 16:022
(@psc)
Posts: 14
Active Member
Début du sujet
 

Thanks!
I see that I havn't been clear in my question. I'm trying to copy an Action in this way, not an Activity, or do I miss something?

I could of course use Activity - or project - management for corrective action plans, but I worry that this will not be very clear for my collegues...
What do you think?
🙂


 
Posté : 2 Mar PM 21:033
(@richard-pare)
Posts: 165
Active Member
 

You want copy linked actions from one project to another.
So, you want duplicate actions too.


 
Posté : 2 Mar PM 22:033
(@psc)
Posts: 14
Active Member
Début du sujet
 

Yes, I'd like to duplicate actions with the structure of activities (duplicate action and linked activities) 😆


 
Posté : 2 Mar PM 22:033
(@babynus)
Posts: 14952
Membre Admin
 

Hi,
Your request is not very clear.

duplicate actions with the structure of activities

This is nonsense : action does not include strucutre (wbs) of activities

duplicate action and linked activities

This is already possible : copy links !


 
Posté : 3 Mar PM 22:033
(@psc)
Posts: 14
Active Member
Début du sujet
 

Thank you and sorry if this is annoying,
trying to re-think my idea of managing corrective action plans.
What I really need to do is follow up corrective actions through the following steps that might be assigned to different people:
Keeping track of working time on these would be nice.
1) Stock isolation (e.g. assigned to production manager or quality manager if stock at customers)
2) Root cause analysis (R&D project manager or process responsible or group)
3) Application of solution (impacted process responsible or group)
4) Verification of solution (test operator or process responsible)
5) Validation of solution (director or customer or other)

How would you do that in ProjeQtOr?


 
Posté : 4 Mar PM 14:033
(@babynus)
Posts: 14952
Membre Admin
 

Just define a workflow, with restriction of profil able to change from one status to another.


 
Posté : 5 Mar AM 01:033
Share:
Retour en haut