Hello,
I'm testing this software, but I don't know how change the % progress of activity.
Anybody has a tutorial to help me?
I'm probably following the wrong order .
I need to know:
1 - Which fields the Project Manager need to sign in "progress" session?
2 - Which fields need to be changed to change the percentage of the activity?
Thanks.
Gabriel Santos
ProjeQtOr is work driven.
This means that progress is calculated from work.
Work is distributed upon resource is assignments, defining Assigned Work, and Left Work (initalized to Assigned work)
Progress = Real Work / (Real Work + Left Work)
Real work is defined in Real Work allocation screen, where left work can also be updated.
You can access the online manual with [F1].
You'll find here all expected information.