Activity->Progress : planned end date got a warning =>cannot update the activity

4 Posts
3 Utilisateurs
0 Reactions
2,895 Vu
Kitcat711
(@kitcat711)
Posts: 65
Estimable Member
Début du sujet
 
[#4552]

Hello,
I am trying to make my planning, and right now I am coping with the proper understanding of the progress zone.
For some reason, during my test, I got a warning in the field "planned end date".

On that screenshot I made my best efforts to put in some correct value.
1) What may be wrong with the dates I entered?

When trying to save my activity, I got the error message:

2 )I think that this is due to the "warning sign" in the field "planned end date".
Is that correct?

3) I understood that the "planned" dates are always calculated: no user can modify them directly.
Is my understanding correct?

4) If I want my Gantt chart to be showing the critical path I need to used the "fixed duration" or "regular between dates" mode.
Is my understanding correct?

Other wise I got the activity starting before the predecessor is complete, like here

5) Where can I find a user guide of "how to use that correctly?" for it appears more difficult than I thought.
Thank you.


 
Posté : 03/08/2017 4:33 pm
(@chris_1784997064)
Posts: 50
Estimable Member
 

Hello Kitcat,

you could check this out:
Problem with planned end date


 
Posté : 03/08/2017 7:43 pm
Kitcat711
(@kitcat711)
Posts: 65
Estimable Member
Début du sujet
 

Thank you #Chris,

Your question and the given answer on the link you provided enlighten my "n°1 bullet point" and I thank you for that.
Any Idea about my others points? 😉


 
Posté : 04/08/2017 12:08 pm
(@babynus)
Posts: 14952
Membre Admin
 

2) Yes
3) Yes
4) No, there is no critical patch calculation in ProjeQtOr.


 
Posté : 04/08/2017 12:21 pm