I don't understand... I remove assigned ressources, and It always visible in Real work allocation !!!
When I came back on Activities assigned ressources, the ressources deleted before is always display! In fact, i cannot remove assigned ressources on activities
Is it normal ?
the best is that in project...Only one ressouces is assigned... and on activities link on this project, I have 5 ressources assigned ???? :blink:
problem is with administrativ type project, I change the Type and no problem now!