Forum

Assigned resources
 
Notifications
Retirer tout

Assigned resources

3 Posts
1 Utilisateurs
0 Reactions
2,325 Vu
(@durou-c)
Posts: 468
Contributor
Début du sujet
 
[#3251]

I don't understand... I remove assigned ressources, and It always visible in Real work allocation !!!
When I came back on Activities assigned ressources, the ressources deleted before is always display! In fact, i cannot remove assigned ressources on activities
Is it normal ?


 
Posté : 7 Avr PM 19:044
(@durou-c)
Posts: 468
Contributor
Début du sujet
 

the best is that in project...Only one ressouces is assigned... and on activities link on this project, I have 5 ressources assigned ???? :blink:


 
Posté : 8 Avr AM 11:044
(@durou-c)
Posts: 468
Contributor
Début du sujet
 

problem is with administrativ type project, I change the Type and no problem now!


 
Posté : 8 Avr PM 13:044
Share:
Retour en haut