Assignment RATE when resource is under 1 ETP

2 Posts
2 Users
0 Reactions
1,159 Views
(@bvd)
Posts: 124
Active Member
Topic starter
 
[#8726]

Hi,

I have a resource that is about 0,5 ETP generally available.

Do I need to set the assignment rater to 50 % for each project and each task ?

Or is the rate automatically calculated, sot when I let the 100% rate for a project or a task for this resource, the real assignment will be limited to the 0,5 ETP ?

Regards

 


 
Posted : 03 Feb 2023 10H10
(@marylene)
Posts: 592
Contributor Admin
 

Hi

If you set his FTE to 0.5 then planning will always be capped at 0.5 per day on any project and any activity.

If you assign an allocation rate , you impact his week. So for a resource working 5 days it will only be planned 2.5 days a week.
And it will have to be done on each assignment of each of the projects where it will be planned.

If you assign an assignment rate, you impact his FTE. So for a resource with ETP = 1 then it will only be planned 0.5 per day on the activity.
You will need to modify the rate at each assignment of each project for it to be taken into account.

The three can be combined


 
Posted : 03 Feb 2023 12H45