Hi
On Project level resource allocation the "Start and End" dates are provide but when it comes to Assignment on a particular task/ activity, we need a start date and end date to be given, in order to track how the resource are engaged with task.
Whether this can be customized.
Kindly help on this.
Thanks in Advance.
Saran
Start date for assignement will be determined by planning calcuation from :
- planning mode of activity
- validated dates of activity (for some planning modes, not for default "asap" planning mode)
- dependencies of activities
- resource capacitty and availability