Assistance Needed with Resource Allocation Update

3 Posts
2 Users
0 Reactions
953 Views
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 
[#9323]

Hi,

I recently used the "Replace the allocated resource" feature for one of my team members who moved to another team. After assigning the project allocation from Resource ID 5 to Resource ID 109, I noticed a duplicate entry under Resource ID 109 for Project ID 14.

The issue I'm facing is that activities are still showing under Resource ID 5, despite the replacement with Resource ID 109. I've tried to track the source of this allocation in the "affectation" table but haven't found any leads.

Could you please assist me in identifying the source of this allocation so that I can ensure accurate reporting and mention the new assignee when the original assignee changes teams and we use the "Replace the allocated resource" feature?

Please refer to the attachments for more details.

Note: I've also checked the history, historyarchive, work, assignment, and resource tables without success.


 
Posted : 16 Feb 2024 14H32
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Activities that have real work are kept on origin resource, and copied to target resource with left work


 
Posted : 19 Feb 2024 22H36
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 

Hi,

Thanks for the response. I understand how the system works, but my concern is about tracking the allocation source. I've tried checking the "affectation" table but couldn't find any leads.

Could you please help me identify the source of this allocation for accurate reporting and updating assignee information?

Thanks.


 
Posted : 21 Feb 2024 10H45