First of all, congratulations for such a great job. Very impressed after few days testing Projeqtor. 😉

Right now I am using the Project Templates. I have create the TemplateX project, and add different activities with a validated start and end dates.

My question now is:

If I copy the TemplateX to a RealX project, how could I update automatically the dates of the activities upon to the current date?

I tried to link the activities with the predecessor option, to see if just changing the first activity date everything would change automatically, but not success...

Is it possible to achieve this? Let me know.

Thanks!!

Oliver.


 
Posté : 12 Oct PM 22:1010
(@babynus)
Posts: 14952
Membre Admin
 

If I copy the TemplateX to a RealX project, how could I update automatically the dates of the activities upon to the current date?

You should not plan with validated dates.
Best is to plan activities with workload assigned to resource, but you can also plan with "fixed duration" planning mode.
Then you have at start one single milestone (start) with "fixed" planning and defined validated date. You change just this date and run planning calculation.
That's all.


 