Hi everyone, I wanted to know if once you have entered the projects and resources, the program via a button or other, it automatically schedules the projects and resources or this is an activity to be done manually.
Thank you all
Hello,
When you have informed your projects with the dates and the planning methods, that you have informed your resources with their FTE and their calendar, then yes, ProjeQtOr will generate your planning.
You can do this manually by clicking on the "Activity planning calculation" button on the Planning screen.
You will find more information in the manual Gantt Chart & Planning.
And you can trigger this calculation automatically thanks to the global parameters.
You will find more information in the manual Globals Parameters and the automatic planning calculation.
Do not hesitate to read it. It's a wealth of information!
Have fun !