Forum

Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.

automatical change ...
 
Notifications
Clear all

automatical change of status after booking in real work allocation

8 Posts
2 Users
0 Reactions
10.6 K Views
(@chris_1784997064)
Posts: 50
Active Member
Topic starter
 
[#4714]

Hello all,

is it possible when you book time at ‘real work allocation‘ for the first time for an activity that the status will automatically be set to ‘in progress’? Because normally if you have no more time left, the status will be set with the last booking to ‘completed’.

And we also have one resource, a project service who has also to book time for some projects. If there is no more time left or he set the left time to 0 the activity gets not automatically to ‘completed’ but to ‘cancelled’. As we know this happens only at this one project service. But sometimes if he is allocated as project team to an activity it worked that the status was set to ‘completed’. Can anybody explain why this happens? In the workflow it is possible to set from ‘in progress’ to ‘completed’. And also at other resources it works as it should.
By the way we are using the version 6.4.1

Thanks and regards.


 
Posted : 19 Oct 2017 18H12
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

is it possible when you book time at ‘real work allocation‘ for the first time for an activity that the status will automatically be set to ‘in progress’?

Yes, this is default behavior. You'll see a small green flag that will inform you about the change.
This automation can be disabled in global parameters screen (tab "work")

Because normally if you have no more time left, the status will be set with the last booking to ‘completed’.

This is also available, and set as default behavior. You see a "finish" flag, but it may be stiked if move is impossible (for instance if result is required and not set)
This automation can also be disabled in global parameters screen (tab "work")

And we also have one resource, a project service who has also to book time for some projects. If there is no more time left or he set the left time to 0 the activity gets not automatically to ‘completed’ but to ‘cancelled’.

Because in your workflow, it is the fist status for the corresponding profile that will check item as "done"


 
Posted : 21 Oct 2017 1H19
(@chris_1784997064)
Posts: 50
Active Member
Topic starter
 

Thanks for your help.

is it possible when you book time at ‘real work allocation‘ for the first time for an activity that the status will automatically be set to ‘in progress’?
Yes, this is default behavior. You'll see a small green flag that will inform you about the change.
This automation can be disabled in global parameters screen (tab "work")

This works now. But there is no check in the box and date of handled. Is this a bug? Or is this normal?


 
Posted : 24 Oct 2017 12H26
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

It depends on configuration of your status.
The status must "check handled"


 
Posted : 25 Oct 2017 13H02
(@chris_1784997064)
Posts: 50
Active Member
Topic starter
 

we have in the status checked handled

and also set in the global parameter the "set to first handled / done status" to yes

But still there is no automatically check in the box at handled or done if we book time at ‘real work allocation‘. And also no date will be set.


 
Posted : 09 Nov 2017 14H06
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

On activity type, set handled as locked to ensure it is automatically set from status and never manually changed.


 
Posted : 09 Nov 2017 15H46
(@chris_1784997064)
Posts: 50
Active Member
Topic starter
 

Can you tell me, if you mean this one:

Thanks you.


 
Posted : 13 Nov 2017 18H47
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Yes


 
Posted : 13 Nov 2017 18H54
Share: