Hello Everybody,
I would like to know, if it's possible to creat automaticly some activity when you creat a new project.
I try to explain, when I creat some new project, i creat alway the same activity in this project, is it possible to automatize this manipulation, please ?
A small other question is about hour report, is it possible to use "." and not a ",", please ?
Thank you for your help
Best regards,
Benoit
Hello,
You can make a model of plan, then you could past the planning template at start of your project.
Thierry,
Hi,
What you need exists : define a template project, with activities you need (you can also define links between activities).
Then, just create your new project by copying the template !
The "template" project type exists for this mean : any project leader can copy it !