Automatique Activity on New Project

3 Posts
3 Utilisateurs
0 Reactions
3,958 Vu
(@benoit)
Posts: 13
Active Member
Début du sujet
 
[#557]

Hello Everybody,

I would like to know, if it's possible to creat automaticly some activity when you creat a new project.

I try to explain, when I creat some new project, i creat alway the same activity in this project, is it possible to automatize this manipulation, please ?

A small other question is about hour report, is it possible to use "." and not a ",", please ?

Thank you for your help

Best regards,

Benoit


 
Posté : 18 Juin PM 13:066
CRESSON
(@thierrc49)
Posts: 97
Active Member
 

Hello,

You can make a model of plan, then you could past the planning template at start of your project.

Thierry,


 
Posté : 18 Juin PM 14:066
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

What you need exists : define a template project, with activities you need (you can also define links between activities).

Then, just create your new project by copying the template !

The "template" project type exists for this mean : any project leader can copy it !


 
Posté : 18 Juin PM 15:066