Hello,
I can not define tasks that are reserved for the defined period - that is, that person only works on that activity and can not be cut by another activity.
I have several projects with different tasks where the same person is assigned (for example regular between 2 dates). I need to add an activity where this person must be on an activity for a period. So I created a task over a period of 5 days with 5 days of charges and putting in regular days. However, he plans me for 6 days, which does not interest me.
Is there a solution to my question?
thank you in advance
Try and change priority
The priority of my task is 60. The others on my other projects are 500 and it does not change anything.
I found.
I had to remove the concepts of project and sub-project as well as the notions of activities and sub-activities.
When I change the priority of my task so that the person is booked 5 days out of 5 days, this is the case.