Hi All,
I plan an activity but I cannot see it in my Diary (except if I allocate hrs in Real Work Allocation. What are the prerequisites in order a Project Activity to be visible in diary?
BR,
Vangelis
It is because you did not "assign" work on the activity.
ProjeQtOr is work driven (also called effort driven).
Did you run planning calculation ?
Please show result of right click on Planning Gantt bar for the activity
Thanks a lot!!!
Are other batch processes? e.g. reindexing
BR,
Vangelis
Some CRONnned tasks, to generate alerts (must be start on admin page)