Changing Activity Dates

2 Posts
2 Utilisateurs
0 Reactions
2,451 Vu
(@jackjacobs)
Posts: 1
New Member
Début du sujet
 
[#4524]

I have set up my project in the planning section. Got started and completed a couple of tasks. My project then got shut down for a month. Now I need to change the start dates for the rest of the activities. I can't seem to do this. Can someone please walk me thru it?

Is there anyone that has written a step by step guide for a new user like me?


 
Posté : 22/07/2017 4:27 pm
(@babynus)
Posts: 14952
Membre Admin
 

I have set up my project in the planning section. Got started and completed a couple of tasks. My project then got shut down for a month. Now I need to change the start dates for the rest of the activities. I can't seem to do this. Can someone please walk me thru it?

Run plan ning calculation changing planning start date in the pop-up.

Is there anyone that has written a step by step guide for a new user like me?

No 🙁


 
Posté : 31/07/2017 1:15 pm