Changing number of work hours per day

2 Posts
2 Utilisateurs
0 Reactions
2,724 Vu
 Dan
(@caccia)
Posts: 340
Honorable Member
Début du sujet
 
[#4794]

Hello,
I have been configuring a new instance of Projeqtor, where I'm using workload defined in hours.
I've initialised projects with the workload in hours, but realize now I should have changed the "number of hours per day" field.

Is it possible to change this global parameter somehow without changing all the assigned workloads I entered on my projects ?
:blush:


 
Posté : 21/11/2017 9:01 pm
(@babynus)
Posts: 14952
Membre Admin
 

NO.
Data is always stored in days in projeqtor, and showing hours is always a conversion.
So if you change number of hours per day, displayed value changes


 
Posté : 21/11/2017 9:06 pm