Hello everyone,
I want to know if it's possible for a resource to introduce his work for an activity which is planified in a future period. For exemple, i'm an architect who works on activity this week but the project manager had affect it to me in two weeks. can i introduce my work this week for this activity ?
Thx
Of course. B)
There is no constraint on this side. 🙂
The reallity is so often different from plannification ! 😆
You can also, if you need, enter some real work in the future : for instance for administrative projects (holidays), or if you want to reserve a day for a specific booked activity (training, meeting, ...). This way, you will avoid planning other activiites on this day.
Thx Babynus for the response, but how can i do it ?
Best regards
Just go to the "real work allocation" screen : you will see the activity, and just enter your real work.