Hello Everyone
In a Project Progression section->Expenses and costs , I accidentally entered a value and I can't correct it.
i've joined the image for your context.
Any guidance to change the value boxed in red color ?
Thanks

 


 
Posté : 03/03/2026 8:36 pm
(@babynus)
Posts: 14952
Membre Admin
 

The value on project is consolidated from values on Activities.
So you have to fix values on activites


 
Posté : 03/03/2026 9:01 pm
(@bcgueye)
Posts: 8
Active Member
Début du sujet
 

Merci babynus - J'ai vu


 
Posté : 04/03/2026 12:57 pm