Happy new year guys !
I have two kind of contracts :
- one for people working 5 days (Monday ot firday)
- one for people working 4 days (Wednesday is off)
I have a report pined on my first page that show the colored plannig by ressources.
For people working 5 days, saturday and sunday are greyed out
For people working 4 days, saturdayand et sunday are greyed out but NOT wednseday. How and where do i change the color of this day off
I made a new calendar and i fixed wednesday as a day off and i excpected Projeqtor to greyout this new day like days of weekend.
I made a new calendar and i fixed wednesday as a day off and i excpected Projeqtor to greyout this new day like days of weekend
Yes, it is it.
You just have to select new calandar for corresponding reosurces.
But I'm not sure the color planning takes this into account (it may only show off days for default calendar).
I'll have a look.