Copying Projects or Activities with sub structure - and keeping the assignment days values

2 Posts
2 Users
0 Reactions
2,861 Views
(@lombard)
Posts: 3
Active Member
Topic starter
 
[#2942]

i am experimenting with copying activities and projects, and have notice that assignments are copied but that the assignment days value is not being copied, it just defaults to 0 after the copy. Is it possible to copy the assignment days value as well.

also

is it possible to copy an activity with various sub-activities (and structure) to a separate new project?

Thank you


 
Posted : 20 Jan 2016 17H34
(@babynus)
Posts: 14952
Member Admin
 

I don't reproduce.
When I copy project with assignments; I also copy assigned work.
Of course real work is not copied, but it is normal !


 