Dependencies linking between activities

2 Posts
2 Users
0 Reactions
1,366 Views
(@navver1990)
Posts: 49
Active Member
Topic starter
 
[#8234]

Dear Sir/Madam,

This question is regarding dependencies linking and baselining the planning.
The issue faced by me during project planning and linking is "
after the dependencies linking , whether the linking of dates will be aligned as per the
planning". So I have performed following test case to verify it:

created new project "Test scheduling"
created 4-5 activities and provide start date , allocate resource, enter BL effort.
On validating/baselining nothing happened like change in dates etc. Though i can see my
linking in gantt chart as per the baseline.But the dates are not changed for activities as per the dependency
for activities

So for all the activities,manual Baselined start date and end date need to be filled.According to my view,after initial baselining and as per dependency
dates should get filled automatically for predecessor and successor activities as per reference date.

Thanks,
Naveen

 


 
Posted : 27 Apr 2022 10H56
(@marylene)
Posts: 592
Contributor Admin
 

Which dates do not change? validated? planned?
These dates do not change but when do you do what exactly?
What do you mean by "On validating/baselining" because the baseline and validating the planning are not the same thing.

According to my view,after initial baselining and as per dependency
dates should get filled automatically for predecessor and successor activities as per reference date.

And we have the possibility of recovering the planned dates towards the validated...
try to describe as well as possible, with the ProjeQtOr vocabulary (exact name of the functions used, screenshots... so that we can identify the steps you are doing.

Try reading these very interesting passages from our manual, which you can find online or by pressing F1 directly from your session!

Dates and duration
Planning validation
Baseline
Dependencies


 
Posted : 27 Apr 2022 11H48