Hi,

When I done real work allocation on a day, I entered several field with 0,2, 0,5, ..., the last cell (sum) is green en display 1. I saved the allocation en when the screen display again, sometimes, the sum is not green as you can see in the screenshot (sometimes it is red or grey)

It is not the first time it appended but this time it was on firefox.

have a nice day


 
Posté : 22 Sep AM 11:099
(@babynus)
Posts: 14952
Membre Admin
 

It must be some rounding issue.
Do you have some work on Tickets ?


 
Posté : 22 Sep PM 14:099
(@seb1981)
Posts: 16
Active Member
Début du sujet
 

No tickets, just projects and activity for now.

I knew this kind of rounding issue 🙂


 
Posté : 22 Sep PM 17:099
(@babynus)
Posts: 14952
Membre Admin
 

I could not reproduce but set a fix (some rounding) in V5.1.


 
Posté : 22 Sep PM 17:099
(@seb1981)
Posts: 16
Active Member
Début du sujet
 

Great

Waiting for the next version

Thanks


 
Posté : 22 Sep PM 18:099
Igor
 Igor
(@lysakov)
Posts: 27
Active Member
 

May be something wrong with rounding?


 