Hello,
The planned hours on the timesheet are automatically displayed in the upper left corner.
In your case it is the number 8.
I don't know how reproduce that to display the 8 as the picture ?
I can't put like 4 for task 1 and 4 for the task 2 if we will do 2 tasks during the day ?
You can put what you want in the timesheet as long as it does not exceed the capacity of the resources.
The real work can be different from the planned work.
Okay thank you ,
But I want to display the same 8 like the picture but i didn't know how to do it ,
Can you help me please
hi
please press F1 on the allocation , assignation of ressources and planning screens, on each you 'll get access directly to the friendly manuel to help you.
Sorry, i do not understand what you are trying to do.
Yes i did it , But they don't show how to do it.
It onlu shows that about planned work :
2 - Show planned work
Check this box to display the planned work.
Planned work is indicated over each input cell, on top left corner, in light blue color.
Allows to display the planned working time by day, for the resource assigned to the task.
To be complete :8 indicates that 8 FTE are planified on this task this day
I just want to know how can i get the 8 like in the picture ! that's all
Without any constraint elsewhere for the planification, it suffices simply to plan a task with 8 resources assigned to it with a capacity of work equal to 1 (FTP / ETP) for each (or 1 resource with the possibility to work like 8 people at a time, in full time ( so FTP/ETP = 8 )), you will access to this display. Please check allocation for a resource on a project and assignation on a task to go futher.